← Back to portfolio

3 Druid Ct — Hot Tub Build

Client: Daniel Chitrik · Contract $50,000 (Original $38k + CO#1 $12k) · Deposit $19k paid · Balance $31k · Post-gunite phase
GC Koby — Lchaim Construction
Sales Mordy
Lead Charlie + Anthony
Today 2026-04-28
Critical path Wed-Thu 4/29-30: Mike Cullen returning for piping. After that, Milton + Mike close out wiring + gas. Post-gunite cure ongoing. Charlie sourcing plaster + stone (verify ownership w/ Mordy — was previously Mordy's). Custom cover sourcing this week.

Today's hot items

ItemBucketOwnerStatus

Zones

Allowances & owner-supplied

ItemAllowance / statusNotes